Bluetooth Certification QPRDv3 Qualification Scheme reference document PRDv3 will come into effect on July 1, 2024, what are the specific changes? Please prepare a small bench!


1.  What do you need to know when completing the qualification process after QPRDv3?

1. All products using Bluetooth technology must complete the Bluetooth certification process

2. Become a Bluetooth SIG member (if you are not already a member)

3. Complete the Bluetooth qualification authentication process in the qualification workspace

4. Your customers must know the correct design number (for products that comply with QPRDv3) or the qualified Design ID (for products that comply with PRD 2.3 or earlier) of their products

5. Follow the Bluetooth brand guide to brand your product


2.  You have until June 28 to process your project draft:

(1) Submit your current draft eligibility review:

1. Log in to the Launch Studio

2. Click the Draft Items TAB in the top navigation bar

3. Click the project name

4. Complete the Bluetooth authentication process described in PRD 2.3


(2) If you do not expect to complete the qualification process before QPRDv3 takes effect:

1. Log in to the Launch Studio

2. Click the "Draft Project" TAB in the top navigation bar - select your draft project

3. Record and save QDID and product details of any references used in the project

4. If your project uses the Qualification Process with Required Tests path in Launch Studio, click the Project Actions button and select Export ICS to export the ICS form

5. Store all information in your own records

6. Delete any draft items that are no longer needed


(3) If you have a draft, it is no longer necessary to:

1. Log in to the Launch Studio

2. Click the Draft Items TAB in the top navigation bar

3. Click Project Operations on the right.

4. Click Delete Item

5. In the dialog box that is displayed, click Delete Items to confirm the deletion

6. Please note that any projects started but not completed before the new QPRD takes effect will be deleted. Removing drafts when QPRDv3 takes effect eliminates the risk of accidentally handling invalid old projects (this administrative cleanup reduces the risk and helps the Bluetooth SIG protect interoperability).


3.  According to the new policy, how will I make my products eligible?

Members will complete the following steps to authenticate their products

d3dad117-bc88-4cca-8b82-6770ba678082_.png

4.  Is the previous certification affected?

When the QPRD takes effect on July 1, products that previously completed the Bluetooth certification process correctly will not be affected and will still show up in the Qualified Products database.


BTL technical team has read the alliance requirements, dedicated to serve you, for the product escort!



Relevant information

EU Releases Exemption Guidelines on Removability and Replaceability of Portable and LMT Batteries — Multiple Product Categories Relief Granted
2026-08-04

EU Releases Exemption Guidelines on Removability and Replaceability of Portable and LMT Batteries — Multiple Product Categories Relief Granted

On July 14, 2026, the European Commission published the "Commission Guidelines to Facilitate the Harmonised Application of Provisions on the Removability and Replaceability of Portable and Light Means of Transport (LMT) Batteries" (Commission Notice C(2026) 5032 final). These guidelines aim to provide a uniform interpretative framework for the implementation of Article 11 of the EU Battery Regulat

6G Developments: Past, Present and Future
2026-07-28

6G Developments: Past, Present and Future

The formulation of 6G standards has entered a more concrete phase. At the 3GPP RAN Plenary Meeting held in Singapore in June 2026, the industry made progress in multiple key research areas and finalized the timeline for Release 21, which is regarded as the first standard version expected to formally define 6G.

Overview of EN IEC 61000-4-29:2026
2026-07-03

Overview of EN IEC 61000-4-29:2026

The key focus of the 2026 edition is to address new DC power distribution environments, especially higher-voltage DC systems. It also clarifies test generator capability, duration tolerance, current limitation during short interruptions, inrush current verification, result evaluation, and test report requirements. For products using 24 Vdc, 48 Vdc, 380 Vdc, 400 Vdc, 800 Vdc, or other DC input pow

Privacy Preference Center

We use cookies to allow our website to function properly, personalize content and advertisements, provide social media features, and analyze traffic. We also share information about your use of our website with our social media, advertising, and analytics partners.

View Privacy Policy

Manage consent settings

Necessary Cookies

Uniformly activate

The operation of the website relies on these cookies, and you cannot disable them in the system. These cookies are typically set based on your actions (i.e., service requests), such as setting privacy preferences, logging in, or filling out forms. You can configure your browser to block or prompt you about these cookies, but this may cause certain website functionalities to not work.

Select Language